Wendake, Que. has a river drop of 204 m.
1,500 kW Francis Turbines: $15,000 x 10 turbines = $150,000 + electrical & HUG Pipes = $320,000 all in.
14,900 kW x 365 x 24 hours x 90%= 117,500,000 kWh $300,000/117,500,000 kWh= $.003/kWh Cost
Quebec Rate: ($0.077 - $0.003 kWh) x 117,500,000kWh = $9,000,000/yr Profit